San Miguel Corporation on Thursday said it has started construction on a 1.2-kilometer road that will connect the recently opened Skyway Stage 3 to the North Luzon Expressway connector project despite delays due to pending right of way acquisition.
The company is "working on what's workable" order to reduce right of way delays, located at the Nagtahan to Sta. Mesa areas in Manila, San Miguel President and COO Ramon Ang said
The connection is part of the detailed engineering design of the Skyway 3 project and can be completed in 24 months or less as soon as the issues with landowners are resolved, Ang said.
MORE ON INFRASTRUCTURE:
Skyway Toll Being Studied, Gov't Says After SMC Seeks P274 Maximum
Skyway Stage 3 is Open, Ramon Ang Looks to More Infrastructure Projects
Mega Airport in Bulacan to Run on Solar Power, Says San Miguel
"This connection is vital because it will link two major expressways, Skyway Stage 3 and the Metro Pacific Tollways' connector road project—making accessibility, interoperability, and ease of travel even better for the public," said Ang.
To mitigate delays, Ang said San Miguel would start construction in available areas, he said.
If everything goes according to plan, the connection would be complete before or by the time the NLEX connector road is completed, he said.